Integrated roadmap

Integrates every AI programme workstream plan - adoption, Champions, learning, knowledge, platform, agent delivery, governance and value - into one dated delivery plan with milestones, a critical path, cross-workstream dependencies and a baseline that changes only by decision. Use when workstreams plan separately, when nobody can say what the next milestone depends on, or when the strategic roadmap needs turning into a plan people can run.

Department
Programme Management
Lifecycle
Mobilise, Enable, Deliver, Launch
Maturity
adopter, builder, scaler, ai-enterprise
Risk tiers
0, 1, 2, 3, 4
Platforms
platform-neutral
Editions
starter, scale, enterprise
Reviewers
none
Status
draft
Copilot Cowork
Programme Management plugin for Copilot Cowork, or this skill on its own: Download SKILL.md
Licence
CC BY 4.0, by Simon Foote

Purpose

The strategic AI roadmap says what will happen in which horizon; a programme also needs a plan that says what happens in which week and what each milestone waits for. This skill integrates the workstream plans into one dated delivery plan with milestones, a critical path and the dependencies between workstreams, and sets a baseline that changes only by decision. Integrated plans go wrong when they are a stapled collection of workstream plans, when the dates come from hope rather than capacity, or when they track activity and lose sight of the outcomes the roadmap serves.

When to use

When not to use

Questions to ask first

  1. Which strategic roadmap initiatives fall within this programme's charter, and which horizon is committed?
  2. What plans do the workstreams already have, at what level of detail, and who owns each?
  3. Which dates are fixed by something outside the programme (a licence renewal, a contract, a business event, a regulator), and which are targets?
  4. Which scarce roles (business owners, knowledge owners, reviewers, makers) do several workstreams need at the same time?
  5. Who can approve a change to the baseline?

Required inputs

If a workstream has no plan, record its milestones as [To confirm: ...] with the owner who will supply them, and show the gap on the plan rather than inventing dates.

Decision framework

Integrate at the level of milestones, not tasks. A milestone is a verifiable state ("knowledge sources for the HR agent have owners and a review date"), not an activity ("work on knowledge").

ElementRule
MilestonesEach has an owner, a definition of done and the evidence that shows it; three to eight per workstream per quarter
DependenciesOnly cross-workstream or external links; each has a giver, a receiver and a need-by date
Critical pathThe longest chain of dependent milestones to the next gate or launch; managed weekly
Capacity checkNo scarce role is committed beyond its declared time in any month, with a reserve for supporting what is live
Fixed and target datesMark which is which; only fixed dates may be shown without a confidence range
BaselineSet after the board approves the plan; changes beyond tolerance need a recorded decision

Typical cross-workstream links worth checking in every AI programme:

ReceiverUsually depends on
Copilot launch waveTechnical readiness, approved-use guidance, Champions in place, support route ready
Agent releaseKnowledge sources ready, evaluation set agreed, reviewer slots booked, owner and support named
MeasurementBaseline captured before the change it measures
Champion learningScenarios and approved-use guidance published
Scale-out to a new unitA scale-or-stop decision on the pilot

Practitioner approach

Collect the workstream plans as they are and do not rewrite them. Ask each lead for their milestones over the committed horizon, the definition of done for each, and what they need from others. The integrated plan sits above the workstream plans; it does not replace them, and workstreams that feel their plans have been taken over stop maintaining them.

Lay the milestones on a single timeline grouped by workstream, then walk the dependencies. For each milestone ask "what must be true before this can happen, and who makes it true?". Most AI programme slippage comes from the same few links: an agent cannot be tested because knowledge owners have not cleaned the content, a Copilot wave cannot launch because the support route is not ready, a benefit cannot be shown because nobody measured the baseline. Draw these links explicitly and give each one to programme-management:dependency-management to track.

Find the critical path to the next stage gate or launch and say plainly which milestones are on it. These get weekly attention; everything else is reviewed at the workstream meeting. If the critical path runs through a single scarce role, such as the only security reviewer, that is a capacity risk to record, not a scheduling detail.

Test the plan against capacity before anyone sees dates. Add up what each scarce role is committed to by month and compare it with what they have declared. Business owners and knowledge owners are usually more constrained than makers. Where demand exceeds supply, move milestones or reduce scope; do not assume people will stretch, and keep time for supporting what has already been released.

Show confidence honestly. Fixed external dates appear as dates; everything else gets a target with a range until the work is understood. Product-dependent milestones carry a note of the capability relied on and the source record checked, because Microsoft release timing is outside the programme's control.

Agree the plan at the programme board and baseline it. From then on, report progress against the baseline, forecast honestly, and bring changes beyond tolerance to the board as decisions rather than quietly moving dates. Re-baseline at each stage gate, and keep the link back to ai-strategy:ai-roadmap so a change in the plan that affects an outcome is visible to the people who own the strategy.

Outputs

Microsoft platform considerations

Milestones that depend on a Microsoft capability, a release wave or a licence change are marked as such, with the capability relied on and the source record checked. Do not schedule against a feature's expected availability from memory; check references/sources.md and track the link through programme-management:dependency-management.

Adoption considerations

Give adoption milestones the same standing as build milestones. Plans dominated by technical go-lives tend to schedule launches without the communications, Champions and manager enablement that make them land.

Knowledge considerations

Treat knowledge readiness as milestones with owners, placed before the agent and Cowork milestones that need it. Content clean-up routinely takes longer than build, so give it its own confidence range.

Security and privacy considerations

Reviewer slots for security-privacy and, where needed, privacy assessment are booked milestones on the plan, not assumed. Store the plan with programme records; it should name roles, not individuals.

Responsible AI considerations

For tier 3 and 4 solutions, schedule the responsible-ai review and any risk acceptance decision as milestones on the critical path. A plan that leaves them to the week before launch invites pressure to waive them.

Evaluation requirements

Not applicable to the plan itself; it must show the evaluation milestones each solution needs (evaluation set agreed, results reviewed) before its release milestone, held by evaluation-quality from risk tier 2.

Value measures

Track milestone predictability (share of milestones met within their confidence range) and critical path stability at programme level, reported by the AI Programme Manager to the board. Baseline capture milestones protect the later value case.

Scale notes

Starter

One page: a dozen milestones across three or four workstreams over a quarter, with the main dependencies drawn and a monthly check at the working group.

Scale

A milestone plan per workstream rolled up into one integrated view, a named critical path, a capacity check by month and a formal baseline agreed at the programme board.

Enterprise

Integrated plans per tranche and business unit rolled up to a programme view, with a planning office maintaining the baseline and cross-unit dependencies reviewed at the portfolio board.

Hand-offs

Reviewer gates

Not applicable, because the plan releases no solution; it schedules the security-privacy, evaluation-quality, responsible-ai and design-authority reviews its solutions need, from the risk tiers those departments set.

Failure modes

Sources

references/sources.md in this skill lists the source records behind this skill, what each is authoritative for, how volatile it is and what you may do with it. Product availability, licensing, limits and preview status change often, so check the current source before stating them, and cite what you used.

Never

Source records for this skill

Microsoft Copilot adoption resources

Microsoft Copilot Studio guidance documentation

Credit

This skill was created by Simon Foote as part of CopilotForge, licensed under CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Credit the author when you share or adapt it.